01.
The challenge
Open land on the edge of Binfield, close to historic buildings.

The site lies on the north side of Tilehurst Lane, just outside Binfield’s village boundary and close to a number of listed buildings. The scheme had to respect the rural edge of the village and the setting of these historic homes.

02.
The proposal
JPP submitted an outline application for 40 new homes.

The scheme proposed 40 homes, including 10 affordable homes, with access from Tilehurst Lane. The homes are arranged in two groups either side of a large green open space, keeping views through the site to the countryside beyond. The plans also included a children’s play area, new landscaping and a wildlife-friendly pond, with a heritage park open to all. 

03.
The outcome
Outline consent granted on appeal, and the homes are now built.

Despite our proposals, the Council refused the application, so we took it to appeal. The appeal was heard alongside our 53-home scheme on the neighbouring site, and in October 2019 the Inspector allowed both. Detailed plans were approved in 2022, and the site has since been built out by Deanfield Homes.